Latest Finish Time Calculator

Latest Finish Time Formula:

\[ \text{Latest Finish Time} = \text{Total Float} + \text{Earliest Finish Time} \] \[ \text{LFT} = \text{TF} + \text{EFT} \]

seconds
seconds

Unit Converter ▲

Unit Converter ▼

From: To:

1. What is Latest Finish Time?

Latest Finish Time is the latest time at which an activity can be completed without delaying the overall project completion. It's a critical parameter in project scheduling and critical path method (CPM) analysis.

2. How Does the Calculator Work?

The calculator uses the Latest Finish Time formula:

\[ \text{LFT} = \text{TF} + \text{EFT} \]

Where:

Explanation: The Latest Finish Time is calculated by adding the Total Float (the amount of time an activity can be delayed without affecting the project completion) to the Earliest Finish Time (the earliest possible completion time for the activity).

3. Importance of Latest Finish Time Calculation

Details: Calculating Latest Finish Time is crucial for project scheduling as it helps identify the critical path, manage project timelines, allocate resources efficiently, and determine the flexibility in activity scheduling without impacting the overall project completion date.

4. Using the Calculator

Tips: Enter Total Float and Earliest Finish Time values in seconds. Both values must be non-negative numbers. The calculator will compute the Latest Finish Time by summing these two values.

5. Frequently Asked Questions (FAQ)

Q1: What is the difference between Latest Finish Time and Earliest Finish Time?
A: Earliest Finish Time is the earliest possible completion time for an activity, while Latest Finish Time is the latest possible completion time without delaying the project.

Q2: How is Total Float related to Latest Finish Time?
A: Total Float represents the amount of time an activity can be delayed without affecting the project completion, and it's used to calculate the Latest Finish Time by adding it to the Earliest Finish Time.

Q3: What happens if an activity exceeds its Latest Finish Time?
A: If an activity exceeds its Latest Finish Time, it will delay the overall project completion unless other activities can be accelerated to compensate.

Q4: Can Latest Finish Time be less than Earliest Finish Time?
A: No, Latest Finish Time is always greater than or equal to Earliest Finish Time since it includes the Total Float.

Q5: How is this used in critical path analysis?
A: In critical path analysis, activities with zero Total Float have their Latest Finish Time equal to Earliest Finish Time, making them critical activities that cannot be delayed without affecting the project completion.