Formula Used:
From: | To: |
The Scheduled Time Given Probability Factor is a project management calculation that determines the expected completion time of a project activity based on standard deviation, probability factor, and mean time. It helps in creating realistic project schedules.
The calculator uses the formula:
Where:
Explanation: The formula combines the variability (standard deviation) adjusted by the probability factor with the expected mean time to determine a realistic scheduled completion time.
Details: Accurate scheduled time calculation is crucial for project planning, resource allocation, risk management, and meeting project deadlines effectively.
Tips: Enter standard deviation, probability factor, and mean time. All values must be valid (standard deviation ≥ 0, mean time ≥ 0).
Q1: What is the probability factor (Z) in this context?
A: The probability factor represents the number of standard deviations from the mean, indicating the desired confidence level for project completion.
Q2: How is standard deviation calculated for project activities?
A: Standard deviation is typically calculated using the formula: (Pessimistic Time - Optimistic Time) / 6, based on PERT methodology.
Q3: What does mean time represent in project management?
A: Mean time, also called expected time, is the weighted average of optimistic, most likely, and pessimistic time estimates for an activity.
Q4: When should this calculation be used?
A: This calculation is particularly useful in critical path method (CPM) and program evaluation and review technique (PERT) for project scheduling.
Q5: Are there limitations to this approach?
A: This approach assumes normal distribution of activity times and may not account for all project uncertainties and dependencies between activities.